Recent completion of two Permanent Pigging Stations

Recent completion of two Permanent Pigging Stations

Darke Engineering has completed the design and build of two Permanent Pigging Stations. One at Brogborough, near Milton Keynes, and the other near Long Buckby. These pigging stations are situated on the 93km 10” class 900 slurry pipeline which runs from Dunstable to Rugby. Client: Cemex UK

Read more

Major works for Southern Gas Networks

Major works for Southern Gas Networks

Darke Engineering have recently completed works at Warblington PRS for Southern Gas Networks.   The works consisted of replacing the site inlet and outlet pipework, construction of a new regulator base, installing a pressure regulator skid module and pre-fabricated housing together with modifications to existing pre-heat water

Read more

Composite pipe repair for Greystar

Composite pipe repair for Greystar

Darke Engineering Ltd were contracted by Greystar UK Ltd to expose possible corrosion features on an 8” diameter steel pipeline and carry out a repair using the WrapMaster system. The Pipeline is a fuel supply line into a RWE npower station in Bedfordshire. An external defect was

Read more

Project – Cowpen Bewley

Project – Cowpen Bewley

The works at Cowpen Bewley comprise the engineering, documentation, construction, NDT and radiographic inspection, testing and tie-in works associated with the removal of 4 No. water bath heaters and the installation of 4 No. heat exchangers and the connection of 2 No. boiler houses and 1 No.

Read more

Project – Regulator stream replacement

Project – Regulator stream replacement

The works comprise the engineering, documentation, construction, NDT and radiographic inspection, testing and tie-in works associated with the replacement of two 60/19 bar regulator streams and two 19/2 bar regulator streams. The works were carried out within the confines of an existing regulator stream building.

Read more

Project – Temporary pigging facilities

Project – Temporary pigging facilities

Installation of temporary pigging facilities on the 10” 96km slurry pipeline from Kensworth to Rugby. Two temporary stations fabricated; Brogborough and Kislingbury. Tie-ins successfully carried out in a 24 hour shut-down period. Darke Engineering carried out all necessary civil and ground works to facilitate the installation of

Read more