Darke Engineering has completed a Pre-Heat Upgrade project at Leyland Way near Preston, UK.

The upgrade included:

  • Removal of existing water bath heaters (including WBH fluid)
  • Removal of associated inlet and outlet pipework
  • Installation of new Heat Exchangers
  • Installation of new associated inlet and outlet HP pipework including valves
  • Installation of new boiler house
  • Removal of water bath heater’s concrete bases
  • Installation of new Heat Exchanger concrete base
  • New Boiler House base
  • Excavation work for new buried HP pipework
  • New E&I ducting route
  • New paving and footpath

Contact Darke Engineering now for more information

For more information please contact Darke Engineering on +44 (0)1733 246 907 or email: info@darke-engineering.co.uk for a competitive quote for your project.

Title

Leyland Way Pre-Heat Upgrade

Client

Cadent Gas

Cadent logo

Role

Principal Contractor

Duration

May 2024

Gallery