Darke Engineering Ltd were contracted by Greystar UK Ltd to expose possible corrosion features on an 8” diameter steel pipeline and carry out a repair using the WrapMaster system.
The Pipeline is a fuel supply line into a RWE npower station in Bedfordshire. An external defect was discovered during the routine intelligent pig run. By using the WrapMaster system, the customer was able to maintain the product flow whilst the repairs were carried out.
Contact Darke Engineering now for more information
For more information please contact Darke Engineering on +44 (0)1733 246 907 or email: info@darke-engineering.co.uk for a competitive quote for your project.
Title
Composite pipe repair for Greystar
Client
Greystar UK Ltd
Role
Principal Contractor
Duration
2014